Client: Airflow Vector Pty Ltd.,
Contractor: Minh Viet Engineering & Construction JSC.
Project Name: Super Stake Mooring System.
Project Code: 5030.
1. Fabrication Status
Cutting & grinding flange reinforcing bars
Fit-up tooling sets
Finish fit-up 1 set tooling
Finished fit-up & welding
Fairing to correct dimension before surface treatment inside
Done
Deliveried
Cutting & grinding shank plates, fluke plates, spreader plates
Finish fit-up 01 set anchor
Finished fit-up & welding 16/ 66 sets.
Finished fit-up, welding, MPI: 35/ 66 sets.
Continue fit-up & welding work
Continue fit-up & welding work
Prepare for surface treatment & painting.
Fabrication: continue fit-up & welding: 12/ 31 remaining sets
Delivered: 35/66 sets.
Anchor after painting & wrapping.
Finished welding: 8/ 75 sets. Finished fit-up: 28/ 75 sets.
Continue fit-up & welding work.
Finished HDG: 5/ 75 sets. Finished welding: 27/ 75 sets.
Delivered: 27/75 sets
Fabrication: finish fit-up & welding: 29/ 48 remaining sets.
Delivered: 27/75 sets. – Preparing for HDG: 29/48 sets.
Reboring: Holes of flange Ø12mm to Ø17mm
Finish drilling flanges 10mm & blind flanges 6mm.
Cutting & grinding center plates, connection plates, profile pipes.
Fit-up center plate to connection plate.
Finished fit-up & welding 01/ 72 sets
Finished welding: 04/ 72 sets. Finished fit-up: 10/ 75 sets
Finished welding: 13/ 72 sets.
Finished fit-up: 24/ 72 sets.
Finished MPI: 13/ 72 sets
Continue fabrication work: fit-up & welding.
Continue fit-up & welding work.
Continue fit-up & welding work.
Delivered: 24/ 72 sets. Fit-up & welding: 24/ 48 sets.
Blasting 8” pipe.